Define the cutover scope, acceptance evidence and restart approvals before requesting bids to replace the main LV switchboard in an operating factory.
Upgrading a factory’s electrical infrastructure to increase production capacity begins with sizing the new main switchboard. The bid also depends on which production lines share a supply and how long a planned outage can last. When seeking quotes from industrial electrical contractors for a factory in Istanbul or another industrial zone in Türkiye, give each bidder the same single-line diagram, load information and outage constraints.
Which loads depend on the existing switchboard?
Map the main low-voltage (LV) switchboard feeders to production lines and auxiliary systems. Compressed air, process cooling and ventilation may each serve multiple lines. Review shift data and production dependencies together. Identify which loads need to stay available, which can accept a scheduled interruption and which will be added as capacity grows. Ask the responsible electrical engineer to review protection and the adequacy of the existing power supply.
What should the electrical bid price separately?
Request separate prices for the switchboard, adaptations to existing cabling, temporary power design where needed, site testing and handover records. Ask bidders which tasks and staff availability determine the planned outage duration. Have production, maintenance and contractor representatives agree on an approval point. If the cutover is deferred, document the permitted operating state, the decision owner and the applicable plan revision. Our switchgear alternatives guide covers how to compare proposed equipment.
What evidence supports a return to production?
Record supplier test results, site verification and the operations team’s restart approval separately in the handover file. Include the circuit identifier, drawing revision, responsible team and outstanding items in each record. IEC 60364-6 is a reference for initial and periodic verification of low-voltage electrical installations. The project team determines the applicable edition and acceptance scope.
The Ulpatek Filter Production Facility is a CANEL industrial reference with documented medium- and low-voltage work. When planning a main switchboard replacement at your own factory, share the single-line diagram, planned capacity increase and production-approved outage windows with the CANEL electrical contracting team.