How to assess switchgear alternatives in factory electrical contracts

Engineer reviewing switchgear alternatives
AI-generated illustrative image.

Technical Guides

Prepared by
CANEL Elektrik
Published
Reading time
2 min

Compare low-voltage switchgear alternatives using technical evidence, procurement lead times and acceptance requirements.

When collecting bids for a new factory in Türkiye, main contractors can find different equipment and delivery obligations under the same line item. Start by identifying the loads the low-voltage (LV) distribution assembly will serve. Then ask bidders to document how their proposed alternative affects the single-line diagram, field connections and commissioning schedule.

Does the same current rating make two assemblies equivalent?

Review the complete assembly. Alongside the rated current, record the project short-circuit level, protection coordination, environmental conditions, cable entries, metering points and any controls interface. Ventilation and maintenance access at the installation location can also affect layout decisions. IEC 61439-2 gives requirements for power switchgear and controlgear assemblies. Specify the verification evidence required by the project separately in the tender documents.

Connect procurement decisions to approvals and site readiness

For each alternative, record the planned order date, manufacturing and shipping lead times, approval documents and the assembly manufacturer’s responsibilities. Where a supplier change affects cable termination, busbar connections or electrical room layout, update the relevant drawings before ordering. On sites with multiple contractors, assign a named owner to the interfaces between switchgear, machinery and building services. Our electrical contracting responsibility matrix shows how to capture those boundaries in a request for quotation.

Agree the factory and site acceptance requirements

Before ordering, establish what will be checked and documented at the factory, which checks will be repeated after installation and who will close open items. Physical layout and labels can be reviewed before dispatch. At site, cable connections, meter points and machinery interfaces can be checked against the installed equipment. Linking the approval record and drawing revision to site acceptance records makes late equipment changes traceable.

Review CANEL’s electrical services and the Yasin Tekstil and Ulpatek scope examples when gathering information for a factory electrical works tender.