Define equipment loads, distribution boundaries and acceptance tests for kitchens and laundries when preparing a hotel electrical tender.
The scope for guest rooms and public areas in a large hotel only covers part of the electrical tender. Ovens, washers, dryers and ventilation equipment may come from different suppliers. Put each unit's electrical requirements and connection point on a shared schedule before comparing quotations.
What information should equipment suppliers provide?
Ask the kitchen and laundry suppliers for the equipment code, supply type, rated load and connection location in writing. Match the code on the layout drawing to the electrical schedule. If selection is still open, state the provisional load, the unit it relates to and who will confirm it. The design team can review operating hours and when equipment is expected to run concurrently. IEC 60364-1 is a reference for the fundamental principles and assessment of general characteristics of low-voltage installations.
Define the boundary between the distribution board and the equipment
Show the relevant distribution board and equipment connection point on the single-line diagram. Identify who runs the circuit to the unit, makes the final connection and attends the supplier's functional test. For ventilation and controls interfaces, state which party provides each signal. Ask for the load schedule, drawing revision and exclusions together when comparing tenders.
Record the acceptance scenarios
Record the supply check, the supplier's functional test and any controls status indication separately. Review opening and peak operation scenarios with the project team. Include the equipment code, board and circuit identifiers, observations and any outstanding items on the acceptance sheet. For refurbishment in an operating hotel, see our guide to phased hotel electrical renovation.