IEA: Data centre electricity demand could double by 2030

Illustration of a server aisle with overhead power distribution
AI-generated editorial illustration.

Electrical News

Prepared by
CANEL Elektrik
Published
Reading time
2 min

The IEA’s November outlook puts data centre electricity use near 1,000 TWh by 2030. What does that mean for grid connections?

Global data centre electricity use could roughly double to 1,000 terawatt-hours (TWh) by 2030, according to the International Energy Agency’s World Energy Outlook 2026, published on 19 November. The figure comes from its Stated Policies Scenario (STEPS). AI investment is accelerating that growth, putting grid connections and electrical equipment procurement at the centre of project schedules.

What does 1,000 TWh measure?

A terawatt-hour measures energy consumed over time. The power a facility needs from the grid at any given moment is measured in megawatts (MW). The global annual figure therefore cannot size a connection for an individual site. Local planning has to account for the opening load, subsequent phases and facility services such as cooling.

Why can the grid connection set the schedule?

Server orders, transformer procurement and grid connections follow different timelines. The IEA identifies constraints in the grid and supply chains, along with public acceptance in some locations. The practical question for a development is how much capacity the proposed connection point can provide and from what date. Completing a data hall and energising the facility are separate milestones.

What information helps at the first project meeting?

During site selection, put the proposed connection point, opening load and capacity for later phases in one schedule. Teams can then distinguish the utility milestone from delivery and acceptance of medium-voltage systems and uninterruptible power within the site. See the data centre electrical tender guide for those scope items.

Sources